The new State Highway 25A Kopu-Hikuai bridge is one other step nearer to completion with the precast concrete facet limitations now in place and additional work to attach the bridge deck to stable floor on the abutments accomplished, says Waka Kotahi New Zealand Transport Company.
The bridge is being constructed to plug a 124-metre-wide expanse that was created after Auckland Anniversary Day flooding was the catalyst for a bit of the freeway to be washed away, closing a most important arterial path to the japanese seaboard.
Building started in June after the Authorities dedicated to fund Waka Kotahi an preliminary value estimate of $30-40 million in Could, which was later revised to be nearer to $50 million.
The announcement of an surprising early completion date on or round December 20 has boosted optimism of an financial restoration within the Coromandel simply in time for the busy summer season interval.
Commercial
Offering a full replace on the week’s work on the Taparahi web site, Waka Kotahi highlighted work being achieved on the bridge’s deck:
“Final week the group lifted and positioned 44 limitations alongside either side of the bridge deck. On the japanese abutment, the group poured the concrete for the growth joint and knock-off block.
“Soil nailing of the slip face above the bridge continues with night time work as nicely to hurry up progress. Drainage set up underneath the bridge and on the western abutment is underneath method.
“The group additionally accomplished the pavement layers for the brand new street on the japanese method. These are the crushed rock layers that can be sealed with a layer of asphalt.
Commercial
“This week, the group will arrange the reinforcement and do the concrete pours, which join the limitations to the bridge deck and type and pour the growth joint and knock off block on the western abutment. They will even begin reinstatement of the street on the western method.
“Asphalt, street marking and limitations can be accomplished over the following few weeks forward of the bridge opening.”
Whereas there was an enormous deal with the brand new bridge, Waka Kotahi mentioned different groups have been working alongside SH25A itself.
“This work will make sure the freeway is in good situation, protected and extra resilient forward of its reopening by Wednesday, December 20. Getting the repairs and upkeep work achieved now means we restrict the impression and disruption our actions have on the street customers as soon as the street reopens.”
By the point the street is reopened the next can have been achieved:
- 23 culverts changed
- 11.5km of facet drains with kerb and channel and riprap drains
- Seven bridges strengthened
- 6.6km of latest seal
- New centre strains, edge strains and edge marker posts had been put in alongside the 28.2km freeway.
Upkeep work on seven bridges alongside SH25A features a new method for strengthening bridges with a high-tech tape “glued” to the underside of the bridge decks (proven above).
Alongside work to restore cracks within the concrete and repaint metal girders, the fibre-reinforced polymer tape is being utilized with high-strength adhesive.
The tape is a relatively new expertise getting used extra broadly as a part of bridge restore and strengthening work throughout the nation.
Scaffolding is in place at every of the bridges so staff can perform different upkeep work to the underside of every bridge.
A time-lapse video of the SH25A mission is accessible here.